c. Armament weapons support equipment (AWSE).
d. Aircraft preparation (loading manuals only).
e. Preparation (weapons assembly manuals only).
f. Release and control system checks (loading manuals only). Release and control system
check procedures shall be prepared as a table <system-checks-table> (standard table) (see
figure 25).
(1) Jettison system check (emergency, selective wing, etc.).
(2) Normal release system checks (parent rack, bomb rack, wing release, ASE
(installed), arming checks, rockets, etc.).
(3) Gun system check (internal, gun pods, crew served).
(4) Missile system check (air-to-ground, air-to-air).
(5) Specialized stores system checks (data pods, ECM, tacts, sonobouys, etc.).
g. Test and reprogramming checks (weapons assembly manuals only).
(1) When applicable, a mission data loading table <mission-data-loading-table>
(standard table) (see figure 26) or mission data downloading table <mission-data-
downloading-table> (standard table) (see figure 27) shall be provided.
h. Individual system checks (loading manuals only). Individual system check procedures
shall consist of the following paragraphs in the order shown.
(1) Test equipment required.
(2) Applicable technical directives.
(3) Check preparation.
(4) Check procedure. Check procedure shall be prepared as a table <system-checks-
table> (standard table) (see figure 25).
i. Postcheck procedures. Explanation that postcheck procedures must be performed upon
completion of the last release and control system check to ensure that the aircraft is returned to a
safe condition and ready to load. Explanatory statement shall be followed by procedural step(s)
as necessary to accomplish postcheck procedures.