MIL-DTL-24784/14B(SH)
b. Instructions required to mount units. Include bolting and bracing diagrams and data on shock
mounts.
c. Instructions for making electrical, plumbing, transmission line, and all other interface
connections (external) to the equipment.
d. Instructions for interconnecting units comprising the equipment.
e. Servicing procedures, such as initial lubrication.
f. Instructions for bonding and grounding.
3.6.3.8.9 Installation checkout. Step-by-step procedures shall be provided to demonstrate that
the equipment operates correctly and within tolerances. These procedures shall provide for
equipment checkout in three test phases as follows:
a. Phase 1 - Installation inspection and pre-energizing procedures.
b. Phase 2 - Turn-on and preliminary tests.
c. Phase 3 - Installation verification test.
3.6.3.8.9.1 Phase 1 - Installation inspection and pre-energizing procedures. When specified in
the TMCR (see 6.2), inspection procedures shall be provided in the form of check lists to verify
the following:
a. That all units of the equipment and required auxiliary equipments have been installed and that
their location and orientation is proper; that all cables, filters, antennas, waveguides,
transmission lines, dehydrators, coolant lines, piping, and so forth, have been installed in
accordance with plans and specifications; that continuity exists in all interconnections.
b. That the test equipment listed in Chapter 1 is on board, operating satisfactorily, has been
calibrated and has adequate storage in accordance with NAVSEA ST000-AB-GYD-010.
c. That the APL is on board, that the Coordinated Shipboard Allowance List includes the
equipment data.
d. That all field changes, ship alterations, and mandatory retrofits have been accomplished.
e. That all installation and reference standards are entered on the Installation Standards
Summary Sheet.
f. That all rotating devices are free from obstruction.
g. That there is access to the equipment for maintenance.
h. That all pre-energizing servicing procedures, including lubrication have been accomplished.
i. That it is safe to turn on the equipment.
3.6.3.8.9.2 Phase 2 - Initial turn-on and preliminary test. Procedures shall be included for
energizing the equipment for the first time. This may be accomplished by reference to the
applicable portions of Chapter 2. Step-by-step procedures shall be included for testing the
equipment electrical supply circuits including distribution panels, switches, breakers, relief valves,
and interlocks. Procedures shall be included for testing piping, electrical cables, wire rope, stays,
for proper installation of transmission lines and waveguides, hangar spacing, torquing of
connectors, pressure testing, flow rates, standing wave ratio and attenuation checks, and so forth.
3.6.3.8.9.3 Phase 3 - Installation verification test. Complete instructions shall be included for
23