MIL-DTL-24784/14B(SH)
testing the equipment in all modes of operation. Where applicable, refer to the scheduled
performance tests in Chapter 4. Procedures shall cover checking gauges, meters, alarms, and
other sensing devices for proper operation and calibration. The tests shall verify that all inputs are
in tolerance. Where applicable, include voltage standing wave ratio and insertion loss tests to
verify the proper installation of antenna-to-equipment waveguide runs; transducer impedance and
source level checks to verify proper installation of transducers, domes, and cables. Preliminary
setup data shall be included in each procedure. When it is required that an alignment be
accomplished prior to performing a test, the alignment shall be included or referenced in the
procedure.
3.6.3.8.9.3.1 Test procedure. Testing procedures shall be presented in a logical order as
follows:
a. Energize the equipment.
b. Test the first units (normally power supplies) which must be operating properly. When test
results are within the required tolerance, include reference to the next logical test. Include a
reference to the corrective maintenance or troubleshooting data to be used if test results are
not within tolerances.
3.6.3.8.9.3.2 Installation standards summary sheet. The installation standards summary sheet
shall provide spaces for recording the results of all installation verification tests and significant
reference standard tests that should be made a matter of record for reference by the technician
during troubleshooting and for a standard to be re-established after overhaul (see figure 14-4).
Each space shall be identified by the step or paragraph number which provides the instructions for
accomplishment. Each space shall contain the respective unit of measurement (for example, amp.,
dB., or V.). When applicable, waveforms shall be included to show the points on the pattern
where the measurement is to be taken. In addition, critical installation data shall be included, such
as the length of the transmission line.
4. VERIFICATION
4.1 Quality assurance requirements. The quality assurance requirements for delivery of book
plans, review draft copies, preliminary technical manuals, final reproducible copy, technical
manuals, replenishment materials, changes and revisions shall be in accordance with
MIL-DTL-24784.
5. PACKAGING
5.1 Packaging. For acquisition purposes, the packaging requirements shall be as specified in the
contract or order (see 6.2). When actual packaging of materiel is to be performed by DoD
personnel, these personnel need to contact the responsible packaging activity to ascertain requisite
packaging requirements. Packaging requirements are maintained by the Inventory Control Point's
packaging activity within the Military Department or Defense Agency, or within the Military
Department's System Command. Packaging data retrieval is available from the managing Military
24
For Parts Inquires call Parts Hangar, Inc (727) 493-0744
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business